Do I need an ADU permit in Orlando, Florida?

Yes. You need a permit.

Yes. You need a permit.

Yes, an ADU goes through Permitting Services. Orlando allows one accessory unit on an eligible single-family lot. Up to 500 square feet needs a smaller minimum lot, and up to 1,000 square feet needs a larger one. The unit must be smaller than the main house. Historic districts cap the ADU at 700 square feet and want a Certificate of Appropriateness first. A new ADU's general sewer impact fee is $1,319.50. School impact fees are exempt. The building-permit price is calculated in the city's portal.

Rules change, and a handout can be older than the code book. This page was checked on November 20, 2026. Confirm it with the local building department before you buy materials or hire someone.

Inside the Orlando city limits. Unincorporated Orange County is a different building department, and its fence and shed rules are not these rules.

Cutoffs they actually printed

What the page says

Fee

$1,319.50 sewer impact fee

The city prints a general sewer impact fee of $1,319.50 for a new ADU. Transportation and park impact fees depend on square-footage tiers. The building-permit fee itself is calculated in the digital portal and is not a single printed number.

Fee source

Who to call

City of Orlando Permitting Services

400 South Orange Avenue, 1st Floor, Orlando, FL 32801

Also in Orlando

Nearby, same question

ADU permit rules by county also covers Phoenix, Berkeley. Rules not published yet — contact the department: Marion County, Florida, Miami-Dade County, Florida, Ocala, Florida, Orange County, Florida, Tampa, Florida, Henderson, Nevada, and Las Vegas, Nevada.

Questions this page answers

Do I need an ADU permit in Orlando, Florida?
Yes, an ADU goes through Permitting Services. Orlando allows one accessory unit on an eligible single-family lot. Up to 500 square feet needs a smaller minimum lot, and up to 1,000 square feet needs a larger one. The unit must be smaller than the main house. Historic districts cap the ADU at 700 square feet and want a Certificate of Appropriateness first. A new ADU's general sewer impact fee is $1,319.50. School impact fees are exempt. The building-permit price is calculated in the city's portal.
Is there a size or height cutoff in Orlando?
Up to 500 square feet: Minimum lot by zoning. Example: R-1 needs 6,000 square feet of lot for an ADU up to 500 square feet. The ADU must still be smaller than the main house. Up to 1,000 square feet: Larger minimum lot. Example: R-1 needs 9,000 square feet of lot. Some zones cannot use this column and must follow the tandem code. Historic district: 700 square feet. Maximum ADU size in a historic district, and a Certificate of Appropriateness comes before the building permit. Sewer impact fee: $1,319.50. General sewer impact fee the city prints for a new ADU.
How much is the permit fee in Orlando?
The city prints a general sewer impact fee of $1,319.50 for a new ADU. Transportation and park impact fees depend on square-footage tiers. The building-permit fee itself is calculated in the digital portal and is not a single printed number.
Who do I call to confirm the adu rule?
City of Orlando Permitting Services. Phone 407.246.2271. Email [email protected]. Rules on this stuff change. Confirm it with them before you buy materials or hire someone.