City of Orlando, Florida
Inside the Orlando city limits. Unincorporated Orange County is a different building department, and its fence and shed rules are not these rules.
Rules change, and a handout can be older than the code book. This page was checked on November 20, 2026. Confirm it with the local building department before you buy materials or hire someone.
Fence
It dependsIt depends, and Orlando printed the cases. A permit is required if the fence is taller than six feet, is concrete, masonry, or block, including reinforced posts, is a pool or spa barrier, is on a corner lot or along a rear alley, is on or near a public easement, has a powered or vehicle gate, is part of a demolition, is in a floodplain or floodway, or is on commercial property or a residential property with three or more homes. The city also says some fences do not need a permit, and those fences still have to follow city code. A historic district or landmark needs a Certificate of Appropriateness before a new fence or a partial replacement. Orange County's 6-foot zoning permit is a different department.
Shed
YesYes. Orlando's residential checklist puts a building permit on the shed. Lights, outlets, or a sink add an electrical or plumbing permit. The page does not publish a square-foot size that skips the permit. A homeowner doing the work signs an Owner/Builder Declaration in person. Over $5,000, file a recorded Notice of Commencement. The shed also has to meet the accessory-structure rules in the land development code, and the checklist does not copy the setback distances onto the permit page.
Deck
It dependsOrlando's small-job exemption, the one for single-family work under $7,500, does not cover elevated decks. The city lists elevated decks with the structural work that still needs a permit no matter the cost. The guide does not say how high 'elevated' is, and the residential checklist does not have its own deck section. A deck that is not elevated is not answered on these pages. Call Permitting Services before you treat a low deck as exempt.
Water heater
YesYes. A water heater is plumbing or gas work, and Orlando says that kind of work cannot use the under-$7,500 building-permit exemption, no matter the price. The city's plumbing permit application has lines for an electric water heater and a solar water heater. The form does not give a gallon or watt cutoff. If the plumbing job is over $5,000 and is not tied to a building permit, a recorded Notice of Commencement has to be on file before the first inspection.
Roof replacement
YesYes. Orlando's small-job exemption does not cover roofing. The city lists roofing with the structural work that still needs a permit no matter the cost, including jobs under $7,500. The guide does not print a square-foot size that skips the permit. You still have to ask the city if you think some other exemption applies, and flood-hazard property is out of the small-job program entirely.
Swimming pool
It dependsOrlando's small-job exemption does not cover pool barriers or fences, no matter the cost. The city's permit-forms page says the usual building forms are used for swimming pools, but the pages checked here do not split in-ground pools from above-ground pools or give a depth that skips a permit. A pool barrier is on the must-permit list. Call Permitting Services before you treat a small above-ground pool as exempt.
Rooftop solar
It dependsOrlando's exemption guide does not name rooftop solar. It does say electrical work is not eligible for the under-$7,500 permit exemption, regardless of cost. A photovoltaic system is electrical work, so that part of the job is outside the small-job exemption. The city does not print a system-size cutoff on the pages checked here.
Driveway
YesYes. Orlando's residential checklist puts an engineering permit on driveways and pavers. A homeowner doing the work without a contractor signs an Owner/Builder Declaration in person. Over $5,000, file a recorded Notice of Commencement. Work on the apron, the piece between the street and the sidewalk, has extra right-of-way details, and the apron has to match the driveway width. The page does not print a dollar fee.
ADU
YesYes, an ADU goes through Permitting Services. Orlando allows one accessory unit on an eligible single-family lot. Up to 500 square feet needs a smaller minimum lot, and up to 1,000 square feet needs a larger one. The unit must be smaller than the main house. Historic districts cap the ADU at 700 square feet and want a Certificate of Appropriateness first. A new ADU's general sewer impact fee is $1,319.50. School impact fees are exempt. The building-permit price is calculated in the city's portal.
Who to call
City of Orlando Permitting Services